All quiet at the works site near Sheriffhall on the Edinburgh City Bypass on 18 September 2013. All preparatory work has now been completed to enable traffic to be switched onto a temporary 4-lane diversionary route in 2 days time, enabling the section in use in the background to be removed. Work will then commence on the installation of a concrete box through which the new Borders Railway will pass. For the view one week later see image 44748.
Location: Sheriffhall City Bypass Overbridge
Original line: Millerhill Deviation (Network Rail)
Photographer: John Furnevel
Contact photographer: John Furnevel
Date: 18/09/2013
Image number: 68120