A rail mounted crane delivers platform portions at Inverness Airport station.

Network Rail has announced that a section of the line between Inverness and Aberdeen will be closed for eleven days to enable work on the Inverness Airport station programme.

Engineers will work around the clock during this time to carry out extensive work between Inverness and Nairn as part of the wider programme of enhancements being delivered around the new station development.

Over a period of 11 days from 23.55 Friday 14th October until the 04.45 on Wednesday 26th October, work will be continuous to substantially complete the new Airport station, to install the passing loop through the station and to enhance sections of track within the area.