Date: 15/06/2019
We're gearing up for another busy phase of activity at #Glasgow Queen Street as the team prepare to extend platforms 2 and 3 by 26m. From 17 June, well uncover space beneath concourse which was 'dug-out' for platform extensions during Queen street tunnel closure. An area at the front of both platforms will be cordoned off to enable this work. We'll also be moving part of the gate-line to the front of platforms 2 to create additional access to the Low Level and Platform1 via Dundas Street. This work is ahead of closing platforms 2 and 3 from 30th June - 29th July. This allows us to extend the platforms to enable longer (8 carriage) electric trains, as well as deliver more seats and faster journey times for customers