Date: 02/05/2008
Following the New Year engineering work, the ORR began an investigation into the overruns at Rugby and Liverpool Street. As a result, Network Rail was fined and a “provisional order” was placed on the company to deliver a robust plan to the ORR by the end of March 2008 for the completion of the West Coast project. Today the ORR has announced that Network Rail has met the requirements of the provisional order, and they consider we have a robust delivery plan in place for the completion of the West Coast project by December 2008